What actually holds up a town planning permit in Melbourne

Objections get the blame, but most town planning permit delays in Melbourne come from documentation gaps. The checklist we run before lodging with council.

A town planning permit is assessed by a council planner who has a queue of files and a statutory clock. Anything that makes your application harder to assess pushes it down that queue. Anything missing stops the clock entirely. So the fastest applications aren't the ones with the most agreeable neighbours — they're the ones that arrive complete.

Here's what actually causes delay, in rough order of how often we see it.

1. Incomplete lodgement

Councils issue a Request for Further Information when a submission is missing something. The statutory clock pauses until you respond, and the planner moves on to the next file. Each RFI realistically adds three to six weeks, and it's entirely avoidable.

The most commonly missing items are a proper existing conditions plan, shadow diagrams at the right times, garden area calculations, a written ResCode assessment against Clause 54 or 55, and a neighbourhood and site description. None of these are optional. All of them get left out of applications prepared in a hurry.

2. Calculations that don't reconcile

A planner will check your numbers. If the garden area calculation on the site plan says 35% but the areas shown don't add up to that, or if the private open space nominated for Unit 2 overlaps with the driveway, the application stops. Not because the design is bad, but because the documentation contradicts itself.

This is the least glamorous part of preparing town planning drawings and the part that most determines how fast a permit issues. We reconcile every number across every sheet before lodging.

Worth knowing

Garden area has quietly become the number that caps yield on more Melbourne blocks than any other single control. Check it before you fall in love with a layout.

3. An overlay nobody checked

Zones set the broad expectation. Overlays change the rules. A Heritage Overlay, Significant Landscape Overlay, Design and Development Overlay, Special Building Overlay or Bushfire Management Overlay each brings its own requirements, and some of them will reshape a footprint entirely.

We do a title search and a planning scheme check before quoting, because finding an overlay in week one costs nothing and finding it in month three costs a redesign.

4. Covenants and Section 173 agreements

Plenty of older Melbourne titles carry a single dwelling covenant. If yours does, no amount of good design will get a two-dwelling application approved — the restriction has to be removed or varied first, which is a separate and often difficult process. Read the title early.

5. A design that ignores the neighbours' entitlements

Your neighbours have specific, quantified protections under ResCode: northern light to their living areas, private open space that isn't overshadowed, and windows that aren't directly overlooked. A design that breaches these will attract both objections and planner resistance, and the two compound.

Designing within those entitlements from the start is not a compromise. It's the difference between a permit in four months and a permit in fourteen.

6. Then, sometimes, objections

Advertising is required for many applications, and objections do happen. But a well-documented application that complies with the planning scheme is defensible — and if a matter goes to VCAT, the quality of the documentation is a large part of what you're standing on.

The checklist we run before lodging

  1. Title and plan of subdivision reviewed — covenants, easements, Section 173 agreements.
  2. Zone and every overlay confirmed against the current planning scheme.
  3. Feature and level survey obtained where the site has fall or existing structures.
  4. Garden area, site coverage, permeability and private open space calculated and cross-checked.
  5. Shadow diagrams prepared at 9am, 12pm and 3pm on the equinox.
  6. Neighbourhood and site description drawn, with neighbouring windows and open space shown.
  7. Written ResCode assessment addressing every relevant standard.
  8. Pre-application meeting with the council planner where the project warrants it.

None of this is exotic. It's just thorough. And thoroughness at lodgement is the cheapest time you will ever buy on a planning permit.

Want us to check the zone and overlays on your site? See our town planning Melbourne service, or send us the address — no charge for the first look.

Ask us
More from the journal

Keep reading

All articles
Dual occupancy Melbourne: is your block big enough?

Dual occupancy Melbourne: is your block big enough?

Read the article
Building permit vs planning permit Melbourne, explained

Building permit vs planning permit Melbourne, explained

Read the article
Orientation: the free upgrade most new homes skip

Orientation: the free upgrade most new homes skip

Read the article
Got a question we haven't answered?

Ask us directly. It's free.

(03) 9070 4747